Case Studies

Dr Pepper

TEAM

ORS Multidisciplinary Team

Sector

Related Services

Fire Safety, PSDP and Assigned Certifier

People To Contact

Overview of service

This world-class manufacturing plant will act as an international operations hub for soft drinks maker Keurig Dr Pepper. Located in Newbridge, Co. Kildare, the warehouse building is 300,000 sq. ft. on a site of approximately 7.42 ha.

Alder Glover Limited appointed ORS as the lead design team to provide Fire, Disability Access, PSDP and Assigned Certifier services for the development.

The application scheme is for a 7-year permission to facilitate the change of use of a permitted warehouse distribution centre to a beverage manufacturing facility and ancillary works to be delivered in two phases. The application also includes an element of retention to regularise additional office and warehouse floor areas beyond those areas previously permitted.

Screenshot 2023 02 13 at 10.25.00
Farran Mullingar
Screenshot 2023 02 13 at 10.25.00

In summary, the proposed development comprises of:

  1. Conversion of the warehouse building into a production and warehouse facility to produce beverage concentrate. 
  2. Construction of barriers at the southwest and southeast corners of the site.
  3. Construction of a tank farm and pipe bridge infrastructure for the storage and transportation of raw materials.
  4. Construction of a new wastewater treatment facility.
  5. New fire water retention pond.
  6. New perimeter security fence; and
  7. Provision of all ancillary development works, above and below ground

The project is an excellent example of how the firm delivers complex multidisciplinary solutions by taking an efficient and simple approach for the client. This involves appointing a project coordinator as a single point of contact for the client.

Group 4987
Castleforbes 3
Screenshot 2023 02 13 at 10.25.00

Project challenges

A phased approach to certification

Getting the project up and running for the client to start manufacturing was a priority. Prior to completion, the ORS Fire Safety Team carried out their final inspections.

The production area was ready for completion, while the ancillary services were not. ORS discussed this challenge with the client and suggested a phased strategy solution. With this approach, ORS introduced two separate completions. The team split the fire sign-off to allow manufacturing to commence. This was also discussed and agreed upon with Building Control. As a result, manufacturing could commence under the BCAR fire safety sign-off of phase 1.

During this new phased approach, a challenge was ensuring that life safety services were fully operational and offering complete cover to the now-finished manufacturing/production area. In the construction zone, however, life safety services needed to remain zoned and/or isolated for the purposes of undertaking specific works. To ensure life safety was never compromised, a temporary solution was utilised to provide cover throughout the construction zone at all times until work was complete and the system went live. Another challenge with continuing construction works within a live environment was ensuring an accessible escape route was maintained through the live construction site. This was successfully managed and executed as a result of appropriate planning and strong communication between all parties.

An innovative approach that came to light on this project was that a production line conveyor belt traversed directly through a compartment line in the manufacturing area. With some clever engineering, a solution was developed in which, on activation of the fire alarm, a slight timed delay was programmed for the engagement of the fire curtain to allow the conveyor belt to mechanically separate and move out of the compartment line. Once complete, the fire curtain would then fully engage, creating the required fire line compartment.

Leaders

Key Contacts

  • Brian Collentine Director 2
    Group 8501 2
    View Bio
    Brian Collentine

    Director

  • Sean Fay Fire Safety Lead
    Group 8501 2
    View Bio
    Seán Fay

    Fire Safety Lead

  • Damian Kenny Commercial Manager
    Group 8501 2
    View Bio
    Damian Kenny

    Commercial Manager

  • Bord Na Mona
    Bord Na Mona HQ

    Fire Safety

  • Lidl RDC Newbridge 05.11.2019 104
    Lidl Distribution Centre

    Fire Safety

  • Centerparcs Forest
    Center Parcs

    Fire Safety

  • Bluebell Apartments 2
    Bluebell Development

    Fire Safety

  • Dr Pepper 2
    Dr Pepper

    Fire Safety

  • PXL 20220803 142743074
    Dublin Airport Logistics Park

    Fire Safety

  • Stemple Exchange 1
    Stemple Exchange

    Fire Safety

Talk to A specialist

Great projects start with great relationships. Have a project in mind? Contact us.

Contact us

Block A, Marlinstown
Business Park, Mullingar,
Co.Westmeath, Ireland.
N91 W5NN

Pembr, 127 Baggot Street Lower, Baggotrath Dublin, D02 F634

Portershed,
Eyre Square,
Galway,
H91 HY51

Office 4, Spencer House,
High Road, Letterkenny,
Co. Donegal,
Ireland. F92 PX8N

Republic of Work,
12 S Mall,
Centre, Cork,
T12 RD43

ORS has satellite offices in Newry and Maynooth.

Back to Top