The extensive development was constructed in a heavily populated city centre adjacent to high-volume trafficked roads and footpaths. There were several risks associated with the demolishing works. These challenges included Asbestos removal and management, site clearance, deep dig excavations, drainage issues, multiple complex structural temporary works, working on multi-story units and minimising any impact on adjacent sites and businesses.
Acting as PSDP, the project had many risks and hazards that the experienced ORS team would have expected to encounter in a complex high-rise project in such a location.
To manage these risks and hazards, the ORS team prepared detailed safety files for the end user based on their requirements concerning various unit uses in residential and commercial areas.